Pharmaceutical company: LIMEDIKA

Pharmaceutical company Limedika chose a GREEN GENIUS solar power plant in the effort to reduce their annual energy costs and benefit from an environment-friendly, renewable energy solution.

Installed capacity: 140,4 kW
Energy demand: the energy produced by the solar power plant will cover 18% of the electricity consumed by the company.
Interesting facts: the rooftop solar power plant can be seen from the Vilnius-Kaunas highway.
Project duration: we have completed the project in 3 months.
GREEN GENIUS investment: 107.000 euros.

Other projects

Brewery: Carlsberg’s Svyturys Utenos Alus

It took 3.703 solar modules and 20 kilometers of cables to install one of the largest solar power plants in Lithuania. Lying comfortably on the rooftop of an iconic brewery in Utena.  Installed capacityt: 1 MW Energy demand: the energy produced by the solar power plant covers 10% of all the electricity consumed by the ...